Challenges
There was stringent safety restrictions implemented by the airport authority due to the fact that the site was situated in a working airport with aircraft in situ to the construction project. The open nature of the project resulted in severe high winds, making working conditions difficult to work. The tight timelines afforded on the project resulted in scaffolding being on the critical path so there was no margin for error in the erection of the project.

“For the YVR A-B Connector project to run on schedule throughout the winter Months we used the Clear Span Temporary Roofing System to cover large areas of the roof to allow for waterproofing to be carried out in all weather conditions.